Define Project Variables
Define and update properties
You can define properties (variables) in the project profile and reference them in formulas.
By defining it in a profile, you can refer to the indicators defined by your organization in each project,
and create plans based on unified indicators.
It can be used as follows.
- Define "standard productivity of documents (time required to create one page)" in the profile.
- Enter the planned output of each item on the work item screen.
- Set the formula for determining the planned ltimes: "standard productivity of document creation x output amount" to calculate the planned ltimes.
This allows you to set the planned ltimes just by registering the planned output amount.
Operation procedure
-
Open the profile setting screen.
It can be set in the administrator screen and project management screen.
The scope of application of the defined value differs depending on the screen you set it in.-
Administrator screen: Can be used in projects to which the defined profile is applied.
-
Project administration screen: Available for the configured project.
If you want to use a standardized indicator for your organization, it is convenient to define it in the administrator screen.Please refer to the following link for the administrator screen: "Manage Profiles"
-
-
If you want to create a new property, click the "+" button to display the creation dialog.
Setting dialog:
Please note the following points when entering.
- If you define "Options", setting a value that is not defined will result in an error.
- If you do not set a "Setting value", set the value using the method described below.
- If you define "Options", setting a value that is not defined will result in an error.
Once a property is defined, it can be edited by double-clicking the "Setting value" in the property screen list.
To edit anything other than the "Setting value", open the item property screen.
The data in the work item must be recalculated.
For details, see the following link. : "Recalculate"
Recalculate
To apply property changes to the entire project,
you must perform a recalculation process using the following procedure.
-
Go to the project profile settings screen (Project - Settings - Profile).
-
Click the Recalculate item formulas button.