Entering item information

Overview

You can also update project information from the timesheet and update it in real time.
Display detailed information about work items in "Item Properties", report progress, and change item information.

Editing an item

First, open the editing screen (Item Properties).
Select the item you want to display and click the "Item Properties" button in the upper right corner of the screen.

  • The displayed values for progress rate, amount of work, etc. are the same as those displayed on the project management screen.
  • The updated values are overwritten as the values for that task and are reflected as is on the project management screen.

Please refer to the following link for the contents that can be operated with item properties.
"Edit item"

Permissions required for editing

To change the value of an item, you need either "Project management" or "Project editing" permission.
If you only have "Project viewing" permission, the following screen will be displayed and editing will not be possible.

  • ①: Indicates that you do not have permission.
  • ②: Value cannot be changed.

If you want to edit a field, you need to take the following action.

  • Grant permission to edit.
    Contact the TimeTracker NX administrator or project manager.
  • Grant partial permission while leaving it as "project viewing permission".
    • Someone with project management permission should set up the following link.
      "Edit items even with project viewing permission"
    • You will be able to edit the following fields.
    • Progress rate, status, actual results amount
      If you want to change a field other than the above

      Ask the TimeTracker NX server administrator to set up the above link.